Purpose – To contribute to the diffusion of Earned Value Management (EVM) as a practicable methodology to monitor facility construction and renovation projects in the context of the European industry. Design/methodology/approach – Firstly, a review of the literature reveals how EVM evolved as a tool for facility construction project monitoring together with specific concerns for its application. Then, a review of EVM practice and trends in Europe are provided and, finally, applicability and viability of the method is proved through a case demonstration. Findings – The EVM practice in the European construction industry is found to be lagging behind other experienced countries and industries despite EVM is found to be applicable, adaptable, and predictive of integrated final cost and schedule of facility construction projects. In particular, cost estimate at completion is forecasted by a simple Schedule Performance Index (SPI) while for the time estimate at completion the Earned Schedule concept is revealed as an accurate predictor. Research limitations/implications – The paper urges the need for research of a European standard as a primary factor for successful diffusion of EVM usage in architecture, engineering and construction projects. Practical implications – This paper helps practitioners to understand the adaptability of EVM practice in the European construction industry and to apply EV tools for effectively monitoring the performance of their projects. Originality/value – Current trends of EVM practice in the European construction context are presented and suggestions for sustaining the diffusion of EVM are given.

Earned Value-Based Performance Monitoring of Facility Construction Projects / DE MARCO, Alberto; Narbaev, Timur. - In: JOURNAL OF FACILITIES MANAGEMENT. - ISSN 1472-5967. - STAMPA. - 11:1(2013), pp. 69-80. [10.1108/14725961311301475]

Earned Value-Based Performance Monitoring of Facility Construction Projects

DE MARCO, Alberto;NARBAEV, TIMUR
2013

Abstract

Purpose – To contribute to the diffusion of Earned Value Management (EVM) as a practicable methodology to monitor facility construction and renovation projects in the context of the European industry. Design/methodology/approach – Firstly, a review of the literature reveals how EVM evolved as a tool for facility construction project monitoring together with specific concerns for its application. Then, a review of EVM practice and trends in Europe are provided and, finally, applicability and viability of the method is proved through a case demonstration. Findings – The EVM practice in the European construction industry is found to be lagging behind other experienced countries and industries despite EVM is found to be applicable, adaptable, and predictive of integrated final cost and schedule of facility construction projects. In particular, cost estimate at completion is forecasted by a simple Schedule Performance Index (SPI) while for the time estimate at completion the Earned Schedule concept is revealed as an accurate predictor. Research limitations/implications – The paper urges the need for research of a European standard as a primary factor for successful diffusion of EVM usage in architecture, engineering and construction projects. Practical implications – This paper helps practitioners to understand the adaptability of EVM practice in the European construction industry and to apply EV tools for effectively monitoring the performance of their projects. Originality/value – Current trends of EVM practice in the European construction context are presented and suggestions for sustaining the diffusion of EVM are given.
File in questo prodotto:
File Dimensione Formato  
Monitoring_Manuscript_R1.pdf

accesso aperto

Tipologia: 1. Preprint / submitted version [pre- review]
Licenza: PUBBLICO - Tutti i diritti riservati
Dimensione 94.67 kB
Formato Adobe PDF
94.67 kB Adobe PDF Visualizza/Apri
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11583/2502327
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo