Contingency budgets are commonly used by managers to respond to uncertainty and control the project within the original cost and schedule targets. However, a variety of project participants with conflicting interests creates tensions when it comes to managing the risk contingency escrow account during the project development, and divergences often arise over the need for either retaining the unspent contingencies (for future risk and improved facility) or releasing it as a profit. With the purpose of studying the dynamics and main influences involved in the risk contingency management process of a design-build (DB) project, a system dynamics (SD) contingency management model is proposed to simulate the decision-making scenarios, under different project conditions and behavioral pressures of senior managers and owners. The model suggests that an aggressive proactive risk management practice might be an effective policy for managing the contingency budget in a complex engineering, procurement, and construction (EPC) project.

Dynamic Management of Risk Contingency in Complex Design-Build Projects / DE MARCO, Alberto; Rafele, Carlo; Thaheem, MUHAMMAD JAMALUDDIN. - In: JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT. - ISSN 0733-9364. - STAMPA. - 142:2(2016), pp. 1-10. [10.1061/(ASCE)CO.1943-7862.0001052]

Dynamic Management of Risk Contingency in Complex Design-Build Projects

DE MARCO, Alberto;RAFELE, Carlo;THAHEEM, MUHAMMAD JAMALUDDIN
2016

Abstract

Contingency budgets are commonly used by managers to respond to uncertainty and control the project within the original cost and schedule targets. However, a variety of project participants with conflicting interests creates tensions when it comes to managing the risk contingency escrow account during the project development, and divergences often arise over the need for either retaining the unspent contingencies (for future risk and improved facility) or releasing it as a profit. With the purpose of studying the dynamics and main influences involved in the risk contingency management process of a design-build (DB) project, a system dynamics (SD) contingency management model is proposed to simulate the decision-making scenarios, under different project conditions and behavioral pressures of senior managers and owners. The model suggests that an aggressive proactive risk management practice might be an effective policy for managing the contingency budget in a complex engineering, procurement, and construction (EPC) project.
File in questo prodotto:
File Dimensione Formato  
JCEM-DynContMng_PrePrint.pdf

accesso aperto

Descrizione: Dynamic management of risk contingency
Tipologia: 2. Post-print / Author's Accepted Manuscript
Licenza: PUBBLICO - Tutti i diritti riservati
Dimensione 589.18 kB
Formato Adobe PDF
589.18 kB Adobe PDF Visualizza/Apri
%28ASCE%29CO.1943-7862.0001052.pdf

non disponibili

Tipologia: 2a Post-print versione editoriale / Version of Record
Licenza: Non Pubblico - Accesso privato/ristretto
Dimensione 400.91 kB
Formato Adobe PDF
400.91 kB Adobe PDF   Visualizza/Apri   Richiedi una copia
Pubblicazioni consigliate

I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.

Utilizza questo identificativo per citare o creare un link a questo documento: https://hdl.handle.net/11583/2619254
 Attenzione

Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo