This work contributes to improving available methodologies for duration and cost estimates of ongoing projects with nonlinear cost profiles. It is demonstrated that accurate time estimates can be made when a generalized mathematical formulation of the Earned Schedule and the point estimate methodology are used. It also highlights the advantages of using these duration estimate methodologies to provide more accurate nonlinear schedule-based cost estimates at completion. This is shown via application and comparison of the proposed methodologies to datasets of eight real case projects from the construction industry. In particular, the defined methodologies tend to perform better, on average, than traditional index-based formulae, especially in the early stages of project development when the practical benefits are the greatest for project teams to take their corrective actions.
Earned schedule formulation using nonlinear cost estimates at completion / Warburton, Roger D. H.; DE MARCO, Alberto; Sciuto, Francesco. - In: JOURNAL OF MODERN PROJECT MANAGEMENT. - ISSN 2317-3963. - STAMPA. - 5:1(2017), pp. 75-81. [10.19255/JMPM01307]
Earned schedule formulation using nonlinear cost estimates at completion
DE MARCO, Alberto;SCIUTO, FRANCESCO
2017
Abstract
This work contributes to improving available methodologies for duration and cost estimates of ongoing projects with nonlinear cost profiles. It is demonstrated that accurate time estimates can be made when a generalized mathematical formulation of the Earned Schedule and the point estimate methodology are used. It also highlights the advantages of using these duration estimate methodologies to provide more accurate nonlinear schedule-based cost estimates at completion. This is shown via application and comparison of the proposed methodologies to datasets of eight real case projects from the construction industry. In particular, the defined methodologies tend to perform better, on average, than traditional index-based formulae, especially in the early stages of project development when the practical benefits are the greatest for project teams to take their corrective actions.File | Dimensione | Formato | |
---|---|---|---|
JMPM013_paper07.pdf
accesso aperto
Descrizione: Manuscript
Tipologia:
2. Post-print / Author's Accepted Manuscript
Licenza:
Creative commons
Dimensione
791.79 kB
Formato
Adobe PDF
|
791.79 kB | Adobe PDF | Visualizza/Apri |
Pubblicazioni consigliate
I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.
https://hdl.handle.net/11583/2674510
Attenzione
Attenzione! I dati visualizzati non sono stati sottoposti a validazione da parte dell'ateneo